COST OF SEDIMENT DISPOSAL FOR THE CITY OF WILSONVILLE
FOR THE WATER TREATMENT PLANT
1. Cost for conducting the TCLP testing on the sediment is taken from the
2000-2001 Schedule of Fees from the Environmental Services
Laboratory ($1180.00/test, plus 25 % add-on for the profit by testing
firms) total of $1475.OO/ day for 15 MGD generated by the treatment
plant.
2. Spencer Environmental Services have quoted $78.00/hour hauling fee,
and indicated 3-hours per truck to haul to and from the landfill. This
comes to $468.00/day.
3. Spencer Environmental Services indicated that the cost of sediment
disposal (Tipping Fee) Is $59.00/ton.
Total estimated cost associated with the "Sediment" that will be generated by
the treatment plant by producing 15 MGD. 2-truck loads of sediment (24
tons/day) will be generated daily for 365 days year.
4. Each truck-load contains 12 ton of sediment x 2 truck-loads
Cost of testing each truck-load $1475/day x 365 days
$538,375.00/year
Cost of hauling to landfill $468 /dav x 365 days
$170,820.0O/year
Cost of sediment disposal/landfill $1416/day x 365days
$516,840.0O/vear
Total Cost/day/year $3359.00/day or $1,226,035.00/year.
Total estimated cost associated with the "Sediment" that will be generated by
the treatment plant when producing 70 MGD, 8- truck loads of sediment (96
tons) will be generated daily (365 days/year).
5. Each truck-load contains 12 ton of sediment x 8 truck-loads:
Cost of testing each truck-load $2950/day x 365 days
$1,076,750.00/vear
Cost of hauling to landfill $1872/day x 365 days
$683,280.00/year
Cost of sediment disposal/landfill $5664/day x 365 days
$2,067,360.00/year
Total Cost/day/year $10,486.00/day or $3,827,390.00/year
Total estimated cost associated with the "Sediment" that will be generated by
the treatment plant by producing 120 MGD, 16-truck loads of sediment (192
tons) will be generated daily (365 days/year).
6. Each truck-load contains 12 ton of sediment x 16 truck- loads
Cost of testing each truck-load $5900/day x 365 days
$2,153,500.00/year
Cost of hauling to landfill $3744/day x 365 days
$131,040.00/year
Cost of sediment disposal/landfill $11,328/day x 365 days
$4,134,720.00/year
Total Cost/day/year $20,972.00/day or $6,419,260.00/year